When possession is delayed beyond the agreed date, the law gives the buyer a choice: leave the project with a refund, or stay and be paid for the delay.
The Real Estate (Regulation and Development) Act, 2016 (RERA) requires a promoter to hand over possession by the date stated in the agreement for sale. Where possession is delayed, the allottee has remedies under Section 18.
The two options
- Withdraw from the project: claim a refund of the amount paid, with interest at the rate prescribed in the State rules.
- Continue in the project: claim interest for every month of delay until possession is handed over.
Compensation for loss beyond interest is decided separately by the adjudicating officer.
Filing the complaint
A complaint is filed before the Rajasthan Real Estate Regulatory Authority for a project in Rajasthan. It should set out the agreement, the promised date of possession, the payments made and the relief sought.
Documents to gather
- Allotment letter and agreement for sale
- Receipts and bank statements showing payments
- Correspondence with the builder about the delay
- The project's RERA registration details
Points to note
A buyer who chooses to continue should keep paying instalments as agreed, unless the authority orders otherwise. Any settlement offered by the builder should be checked against what the law already allows before it is signed.
Questions
Can a complaint be filed if the project is not registered under RERA?
Registration is required for most ongoing and new projects. If a project that should be registered is not, that itself can be raised before the authority.
Is a consumer complaint an alternative?
In many cases a home buyer may approach either the consumer commission or the RERA authority. The better forum depends on the facts and the relief sought.
This article is general information about the law as at 25 November 2026. It is not legal advice and does not create an advocate–client relationship. The law and its application depend on the facts of each case.